Sunday, July 4, 2010

Basement Floor

Good progress this week. The blocks for the garage walls were put up, the in-floor heat was put in the basement, and the basement floor was poured. On Tuesday dad and I put the styrofoam down for the in-floor heat and it was installed on Wednesday. I talked Rob into pouring the floor on a warm day (Thursday) when they would usually wait for a cooler one. This way the carpenters can get to framing and setting trusses next week.